Grid capacity · connection queues · evidence

Where the grid has room.

Substralis puts the room Norway's grid companies publish for new load, Statnett's connection queue against it and the evidence behind both on one map. Every figure links to the source that published it, with its date. The rest of Europe is on its way: see how far each country has come.

Accounts are by invitation during the beta. See how it works

Live example: Jeløy, in Moss, publishes 25 MW of room for new demand . Above it, at Statnett's Tegneby TRA, 4 demand cases wait for 217 MW . Follow the chain

Substralis today

Countries in the works
36
Norway is open; how far the rest have come
Stations in Norway with a figure for new demand
838
of 1,278 stations on the map
Cases in Statnett's register
1,979
1,241 of them at Assessment · Jun 2026: Statnett stopped publishing this stage after its June 2026 edition; the case had not left the register then.
Sources for Norway
36
30 up to date; the latest read 27 Nov, 05:16 UTC

Room

Every light is room an operator published.

838 of 1,278 stations in Norway publish how much room is left for new demand, most through WattApp . Around the Oslo fjord, each label is that figure in MW. The brighter the light, the more room; where nothing is published, the map stays dark.

  • Room published
  • Queue, no room published
  • Operator says full
  • Nothing published

The queue

Behind the room, the queue.

Around Rjukan, each column is a case in Statnett's register : 6 cases for new demand, 3 waiting for 1,153 MW and 3 holding 76 MW reserved; 2 for production. Solid columns are reserved; glass columns are still waiting. The largest demand case: Statkraft Energi AS, 900 MW.

Assessment · Jun 2026: Statnett stopped publishing this stage after its June 2026 edition; the case had not left the register then.Statnett's register also holds 1,241 cases at its assessment stage: requests and preliminary assessments it stopped publishing after its edition of 24 June 2026. They had not left the register, so the portal keeps and counts them, each tagged; the map here draws the queue and the reservations.

  • Reserved
  • Waiting in the queue
  • Production

The chain

Room is local. The queue is not.

Jeløy, in Moss, publishes 25 MW available for new demand . Elvia says it hangs from Tegneby TRA, 10 km away . At Tegneby TRA, 4 demand cases are waiting for 217 MW, 7 cases hold 719 MW already reserved, and 20 are at assessment (134 MW) . Statnett publishes no headroom at Tegneby TRA: the room at Jeløy depends on it all the same. Open Jeløy in the portal

Evidence

Every figure opens its source.

Click a source chip, like this one , to see who published a figure, under what licence and when we last read it. Missing stays missing: north of the Arctic Circle, 84 of 151 distribution stations publish a figure for new demand, and the rest stay dark. A figure that isn't published is shown as not published, never as zero or as free.

Norway first. The rest of Europe next.

Norway is open to everyone. Denmark, Sweden, Finland, Britain, the Netherlands, Germany, Ireland and France are on the map for accounts, which are by invitation while we bring each one up to Norway's depth; 28 more countries are being read and checked. Each keeps its own unit and grain: MW stays MW, MVA stays MVA, a forecast keeps its year.

  • NorwayHeadroom at substations, and every case in Statnett's queue838 stations with a figureOpen to everyone
  • DenmarkHeadroom at substationsNearly completeBy invitation
  • SwedenCounty capacity to 2035, and connection bands at stationsPartialBy invitation
  • FinlandHeadroom at substations, and main-grid capacity by yearPartialBy invitation
  • Great BritainHeadroom at substations, and the connection registersNearly completeBy invitation
  • NetherlandsOfftake status per feeding areaPartialBy invitation
  • GermanyForward connection bands at transmission stationsEarlyBy invitation
  • IrelandHeadroom at distribution nodes, in MVAPartialBy invitation
  • FranceOfftake capacity per RTE consumption zonePartialBy invitation

Every country, and how far each has come

Read from the people who run the grid.

Grid operators and regulators publish these figures on their own schedules, from daily to yearly. Substralis reads each one on its timetable, keeps the date on every figure, and flags a source that stops answering. Today 30 of the 36 sources for Norway are up to date.

  • WattApp capacity map

    Elbits AS for 42 Norwegian DSOs

    Available capacity at DSO substations, for new demand and for new production, as each DSO publishes it. WattApp stamps every figure with the moment it serves it; it publishes no separate effective date.

  • Connection queue and reservations

    Statnett SF

    Every consumption and production case in Statnett's queue: customer, MW, sector, status and dates.

  • Grid asset register (Nettanlegg)

    Norwegian Water Resources and Energy Directorate (NVE)

    Official geometry of transmission and regional lines, sea cables and transformer stations, with owner and voltage.

  • PlanNett area studies

    NVE, with each study's grid companies

    Grid area studies registered in NVE's PlanNett: who wrote each study, the stations it names and the measures it plans. The study's own texts are in the document.

  • Hydropower database

    NVE

    Every Norwegian hydropower plant in operation: installed MW, owner, gross head, river and year.

  • Business grid tariffs

    NVE (tariffs reported by each grid company)

    Each grid company's high-voltage business tariff per county: demand charge, fixed charge and energy charge, as published, excluding taxes.

Every source, market by market · How each one is read

The whole map is in the portal.

  • Map and list

    Every station in Norway with its figure, narrowed to the MW you need.

  • Station dossier

    The room, the station it depends on, the queue there stage by stage, and the evidence for each figure.

  • Memos

    Freeze a finding into a memo and share it as a link or a PDF.

  • Watch

    Follow stations, companies and areas; the briefing shows what changed since you last looked.

During the beta, accounts are by invitation.

Or write to hello@substralis.com.