Markets · NO

Norway

Norwegian distribution companies publish the room left for new demand at their substations, and Statnett publishes every connection case at its transmission stations, with the customer's name.

Stations on the map
1,278
With a figure for new demand
838
Cases in Statnett's register
1,979
1,241 of them at Assessment · Jun 2026: Statnett stopped publishing this stage after its June 2026 edition; the case had not left the register then.

In Substralis now

  • Loaded: published headroom
  • Loaded: the named queue1,979 cases
  • Loaded: parent-station links

Map

Map of Norway: stations that publish room glow amber.

The live map of Norway, with every station's figure, its queue and the station it hangs from, is open to everyone. Explore it.

  • Room published
  • Queue, no room published
  • Operator says full
  • Nothing published

A still of the map: stations that publish room glow amber. The lists below give the largest figures.Figures as read 27 November 2026

What Norway publishes

  • Available capacity for new demand at distribution substations, through WattApp
  • Which Statnett station each of those substations hangs from, as the distribution company states it
  • Every consumption and production case in Statnett's queue: customer, MW, sector, status and dates
  • The transmission and regional grid, transformer stations and every hydropower plant, from NVE

What it doesn't

  • A comparable headroom figure at every Statnett station: the area studies describe some in words
  • Queue positions: Statnett publishes status and dates, not rank
  • Organisation numbers for queue customers

How Substralis reads Norway: units, dates and the chain

Network operators

Norway: 78 distribution operators in NVE-RME licensees and revenue-cap input data. Which of them publish station figures is counted when the market's station index is next built.

Distribution operators by stations on the map with a published figure
OperatorStations on the mapWith a published figureWhat we hold
ELVIA AS——Not counted yet
GLITRE NETT AS——Not counted yet
BKK AS——Not counted yet
LEDE AS——Not counted yet
TENSIO TS AS——Not counted yet
LNETT AS——Not counted yet
ARVA AS——Not counted yet
LINJA AS——Not counted yet
NORGESNETT AS——Not counted yet
FAGNE AS——Not counted yet
TENSIO TN AS——Not counted yet
FØIE AS——Not counted yet
LINEA AS——Not counted yet
NORANETT AS——Not counted yet
ELINETT AS——Not counted yet
MELLOM AS——Not counted yet
NETTSELSKAPET AS——Not counted yet
VEVIG AS——Not counted yet
MIDTNETT AS——Not counted yet
ELMEA AS——Not counted yet

58 more in the register. Every operator, with its size and sources, is in the signed-in portal.

Most room published

Available capacity for new demand, as each operator publishes it
StationOperatorRoomSource
SmølaMellom148 MW
HålandLnett68 MW
SvolværElmea67 MW
LidalSygnir66 MW
GrønlandElvia63 MW
PilestredetElvia58 MW

Where the queue is longest

Room at a substation depends on the Statnett station above it. These Statnett stations have the most new demand waiting in the queue ; the substations below them publish their own room , and say which station they hang from .

Demand cases at each station, as its page in the portal counts them. Waiting and reserved are two stages and are never added together.
Statnett stationDemand waitingDemand reservedSubstations below, with room
Grenland TRA1,157 MW · 5 cases61 MW · 23 of 7
Rjukan TRA1,153 MW · 3 cases76 MW · 30 of 3
Nedre Røssåga KRA/TRA1,010 MW · 3 cases31.2 MW · 3—
Vardal TRA729 MW · 16 casesNone0 of 2
Orkdal TRA585 MW · 4 casesNone10 of 14
Arendal TRA507 MW · 4 cases88.5 MW · 113 of 18
Marka TRA500 MW · 1 case349 MW · 4—
Eidum TRA490 MW · 2 cases9.2 MW · 15 of 9

Sources